Plastic sheet equipment operation should pay attention to the link:
1. Plastic sheet equipment Operators should be trained, familiar with the use of mechanical equipment structure, performance and use.
2. Plastic sheet equipment before the test machine, the parts of the normal operation of the operation before the boot must be the machine around and under the operating area of the debris clean up, when necessary in the operating Area Matting board.
3. Must use directional switch, forbid to use reverse switch.
4. Chain, gears and belts and other transmission parts, you must install a protective shield or protective board.
5. Clean the wood shavings and sawdust on the table of plastic sheet equipment.